INSTALLATION AND ARRANGEMENT OF THE TWO HV CABLE FROM GIS OUTDOOR AG. NIKOLAOS TO THE NEW ADG SUBSTATION

alouminio-elladas-3

The scope of the AG NIKOLAOS CCGT II - ADG INTERCONNECTION project, of the MYTILINEOS S.A. group, includes the installation and arrangement of the two HV cable circuits (400kV) and the earth continuity conductors from GIS OUTDOOR Ag. Nikolaou to the new ADG Substation, in the Aluminum Hellas industrial facility.

In the role of TEKAM GENIKI ENERGY S.A. is to perform the following tasks:

• Installation and arrangement of 400kV HV cables (2 circuits, total 12 HV cables and 2 earthing cables), according to the plans

• The placement of link boxes & surge arresters

• Installation of earthing continuity cables for the 2 circuits

• Lifting and tying the cables to the scaffolds sealing ends

• Arranging and tying the cables to the metal supports

• Positioning and tightening of cable clamps

• Carrying out a sheath test on all cables after the completion of the casting and before the installation of the terminal boxes

Tekam Geniki Energy SA, is a construction company focusing on Power Generation Plants, Petrochemical Facilities, Gas Facilities and Metallurgical factories in Greece and abroad.

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.